Data centers and mission critical
Hyperscale and colocation campuses, built in phases, where the date that matters is the day the first hall carries IT load.
- Clients
- Hyperscale owners and colocation developers; GCs; MEP contractors; commissioning agents
- Markets
- Northern Virginia, Phoenix, Dallas-Fort Worth, Columbus, Atlanta, Chicago, Dublin, West London
Scope
Shell and core first. Then the electrical and mechanical fit-out that makes up most of the cost: medium voltage switchgear, transformers, generators, UPS, busway, chillers or air-cooled plant, fan walls or CRAHs. More and more often, liquid cooling to the rack as well.
On a repeat campus the same design gets built several times. Building three should go faster than building one. The people who make that happen are the people clients ask us for.
Seats on a campus program
- Program Director, owner side
- Project Director
- Construction Manager
- MEP Director
- Commissioning Manager
- Electrical Superintendent
- Mechanical Superintendent
- Owner's Representative
- Project Controls Director
- Preconstruction Director
- Quality Manager
- VP Operations for a mission critical unit
Metros
All six US metros on our list. Also Dublin and West London. Northern Virginia has the deepest pool of people who have done this several times over, and they get approached constantly. Elsewhere the pool is thinner and relocation is part of most conversations.
Evidence we look for
- Taken at least one data hall through Level 5 integrated systems testing and handed it to an operations team that then ran it.
- Managed owner-furnished, contractor-installed equipment. Tracked factory witness tests and delivery slots, found somewhere dry to store it, and sorted the paperwork when a generator arrived with the wrong breaker settings.
- Worked to a utility energization date, and re-sequenced the job when it moved.
- Built the second or third building on a campus and can say exactly what changed from the first.
- For superintendents, run electrical or mechanical trades at the scale of several hundred workers on one site.
- For commissioning roles, written test scripts, run load bank tests, and closed out an issues log with the owner's commissioning agent across the table.
Timing the approach
Everyone with real IST experience is busy. The best of them are tied to a phase and will not leave before turnover, so timing an approach around their schedule matters as much as the offer. We keep a rough calendar of where people are in their programs for exactly this reason. A call in the month after turnover gets a very different reception from one in the middle of Level 4.
Expect counteroffers, retention bonuses tied to substantial completion, and hard questions about your backlog. A Commissioning Manager wants to know there is a next building after this one.
Pay and terms
Per diem and travel allowances are normal for superintendents and commissioning staff working away from home. Vehicle allowances are common for site roles. Bonus is often tied to milestones, and candidates will ask which ones.
Commissioning levels, and who runs each one
Owners label these differently. Some split Level 2 in two, some never say "Level 5" and only say IST. The order of work does not change.
| Level | What is tested | Where | Usually led by |
|---|---|---|---|
| Level 1 | Factory witness tests of major equipment: generators, switchgear, UPS modules, chillers | At the manufacturer | The vendor, witnessed by the contractor and the owner's commissioning agent |
| Level 2 | Inspection on delivery, and installation checks against the approved submittals | On site, on delivery then after setting | The installing contractor, with the Commissioning Manager |
| Level 3 | Start-up and pre-functional checks: rotation, terminations, torque, insulation resistance | On site, system by system | Installing contractor and vendor start-up technicians |
| Level 4 | Functional performance tests of each system on its own, through every mode in the sequence of operations | On site | The Commissioning Manager, witnessed by the commissioning agent |
| Level 5 | Integrated systems testing. The whole building under simulated IT load, with failures introduced on purpose | On site, usually with load banks | Commissioning agent and Commissioning Manager together, with the operations team watching |