Hire commissioning and controls leads before the gear arrives
Commissioning leadership on mission critical work is often hired months later than it should be. Here is what that costs, and how to time it better.
The usual pattern
On a lot of mission critical projects the Commissioning Manager is hired when the first switchgear lineup is about to land. It feels logical. Testing starts when there is something to test.
The trouble is that by then most of the decisions that shape commissioning have been made by somebody else. The person you hire inherits them, along with whatever problems they contain.
Decided before anyone is on site
Walk backward from Level 5 and you find a long list of choices made during design and procurement.
- The sequences of operation, and whether anyone who will test them has read them.
- The scope of factory witness testing. Which equipment gets witnessed, by whom, and whether the trip to the factory is in anyone's budget.
- Where the boundary sits between the building management system, the electrical power monitoring system and the vendors' own controls, and who integrates them.
- Point naming and graphics standards, which are painful to change once programming has started.
- The load bank strategy: rented units or permanent connection points, and where the heat goes during a test.
- The format of the turnover package the operations team will receive.
- Where commissioning really sits in the master schedule, as opposed to the four weeks somebody pencilled in before substantial completion.
A Commissioning Manager hired at design development can shape all of it. One hired at gear delivery spends the first two months reading decisions they would have made differently.
Two sides, two jobs
The titles overlap, and that causes bad hires. A brief that says "commissioning lead" without saying which side of the contract the person sits on will attract the wrong half of the market.
| Seat | Sits with | Owns |
|---|---|---|
| Commissioning authority or agent lead | The owner, or an independent firm working for the owner | Owner's project requirements, design review, witnessing, the issues log |
| Commissioning Manager | GC or MEP contractor | The commissioning plan, test scripts, coordinating trades and vendors, closing issues |
| Controls or EPMS lead | Contractor, sometimes the owner | Integration of BMS, EPMS and vendor controls, point-to-point checks, sequences |
| MEP Director | Contractor or developer | Design coordination, packages, installation quality across electrical and mechanical |
People do move between these seats. A strong agent-side lead can become an excellent contractor Commissioning Manager. The move takes some adjusting, though. An agent is paid to find problems. A contractor's Commissioning Manager is paid to close them before the agent finds them.
Controls deserves its own mention. On many jobs the BMS and the EPMS are specified by different engineers, bought in different packages and integrated in the last few weeks before testing, by people who met each other that month. The results are familiar to anyone who has sat through IST: mismatched point names, alarms that land on the wrong screen, and graphics that make sense to the programmer and nobody else. A controls lead who arrives during design can line up point lists and network architecture while changing them costs an email. Later it costs a change order.
When to hire each one
Our rough guide, against a single-building program. A campus with repeat buildings can share some of these people across phases, which changes the cost but not the order.
| Seat | In seat by | Because |
|---|---|---|
| MEP Director | Award, or earlier on a design-build pursuit | Packages and procurement strategy are set in preconstruction |
| Controls lead | Design development | Integration boundaries and point naming are cheap to fix on paper |
| Commissioning Manager | Before the first factory witness test | Level 1 is the first test, and the scripts for later levels grow out of it |
| Electrical Superintendent | Before medium voltage gear deliveries | Receiving and protecting the gear is site work from the first day |
| Quality Manager | Before the first installation | Inspection records are hard to recreate afterwards |
Five interview questions
Each of these has a right kind of answer, which is specific, and a wrong kind, which is general.
- Talk me through the worst Level 5 test you ran. What failed, and what did the fix cost in days?
- On your last job, how was responsibility for the EPMS split between the electrical contractor, the controls contractor and the switchgear vendor? Would you split it the same way again?
- A generator arrives on site with items still open from its factory witness test. What do you do that week?
- The commissioning agent and the GC disagree on whether a test passed. You are in the room. What happens next?
- What did the operations team say about your last turnover package, six months later?
Strong candidates answer with system names and dates. They also tend to say what they would do differently next time without being asked.
Reading the resume
A few signals are worth more than any job title.
- Test levels named explicitly, along with the size of what was tested, in megawatts or number of halls.
- Repeat phases on the same campus, which usually means the client asked for that person back.
- Dates that run through turnover. Plenty of people leave a project just before the hard part.
- Some time at a vendor or a commissioning agency, which gives a contractor-side lead a view from the other side.
And one warning sign. A resume where every project says "oversaw commissioning" and none of them says what was tested.
If you are about to hire into one of these seats, or have just lost someone from one, send us the project stage and the date of the first factory witness test at shannon@maulegrouphq.com. That date tells us most of what we need to know about how urgent the search is.